IAG – all repairs and rebuilds to commence in the next two years

IAG have issued a media release announcing, in general terms, the timetable for their repairs and rebuilds.

IAG is providing further certainty for earthquake affected customers, confirming when in the next two years all residential property reinstatements will begin – with the last scheduled to start no later than the last quarter of 2014.

IAG’s residential rebuild and repair programme involves 1700 rebuilds and 3000 major (overcap) repairs, which the company aims to complete by December 2015.

For more information on IAG’s repair and rebuild timetable, the media release can be found here.

.